Mixing(配料)
Mix solvent and bound separately with positive and negative active materials. Make into positive and negative pasty materials after stirring at high speed till uniformity.
Coating(涂布)
Now, we are in coating line. We use back reverse coating. This is the slurry-mixing tank. The anode(Cathode)slurry is introduced to the coating header by pneumaticity from the mixing tank. The slurry is coated uniformly on the copper foil, then the solvent is evaporated in this oven. (下面的依据情况而定)There are four temperature zones, they are independently controlled. Zone one sets at 55 degree C, zone two sets at 65 degree C, zone three sets at 80 degree C, zone four sets at 60 degree C. The speed of coating is 4 meters per minute.
You see the slurry is dried. The electrode is wound to be a big roll and put into the oven. The time is more than 2 hours and temperature is set at 60 degree C.
Throughout the coating, we use micrometer to measure the electrode thickness per about 15 minutes. We do this in order to keep the best consistency of the electrode.
Vocabulary:
coating line 涂布车间back reverse coating 辊涂coating header 涂布机头
Al/copper foil 铝/铜箔degree C 摄氏度temperature zones 温区
wind to be a(big)roll 收卷evenly/uniformly 均匀oven 烘箱
evaporate 蒸发electrode 极片
Cutting
Cut a roll of positive and negative sheet into smaller sheets according to battery specification and punching request.
Pressing
Press the above positive and negative sheets till they become flat.
Punching
Punching sheets into electrodes according to battery specification,
Electrode
After coating we compress the electrode with this cylindering machine at about 7meters per minute. Before compress we clean the electrode with vacuum and brush to eliminate any particles. Then the compressed electrode is wound to a big roll. We use micrometer to measure the compressed electrode thickness every 10 minutes. After compressing we cut the web into large pieces. We tape the cathode edge to prevent any possible internal short. The large electrode with edge taped is slit into smaller pieces. This is ultrasonic process that aluminum tabs are welded onto cathodes using ultrasonic weld machine. We tape the weld section to prevent any possible internal short. And finally, we clean the finished electrodes with vacuum and brush.
Vocabulary:
cylindering 柱形辊压vacuum 真空particle 颗粒
wound 旋紧卷绕micrometer 千分尺internal short 内部短路
slit 分切ultrasonic 超声波weld 焊接
Anode making
In anode making process, we cut the material into certain length strips. At the mean time, we put a small piece of insulation tape to the tab in order to prevent any possible internal short. Then the prepared nickel tab is riveted on anode and pat plain. We also tape the rivet section to prevent any possible internal short. And finally, we clean the finished electrodes with vacuum and brush.
Jelly roll
This is Jelly roll, a manual winding process. In the course of Jelly roll, firstly, we place the s
eparator in between central pins, press the foot switch to turn central pins about 120 degrees. Secondly, place the anode to the edge of central pins, and turn central pins about 180 degrees. Lastly, place the cathode to the edge of central pins. During the winding process, we apply tension by pressing the electrodes and the separator. We put the termination tape at the end.
After Jelly roll, we check the short circuit, then form the Jelly roll by pressing, so that it is easier to insert the Jelly roll into the can.
Control points:
1. When winding to the end of the anode, covering the anode completely by the separator.
2. In the whole process, it is the most important points to ensure the best alignment among the cathode, the anode and the separator for the Jelly roll. The separator has to cover the anode and the cathode, and the anode has to cover the cathode completely. These points are mainly checked before short checking.
Vocabulary:
Jelly roll 卷绕Manual 手工的Separator 隔膜纸
central pin 卷针foot switch 脚踏开关anode 负极片
cathode 正极片termination tape 尾端胶纸short circuit 短路
alignment 整齐
Taping & inserting
Put the tape on the two side of J/R, To prevent J/R being hurt in the insertion process.
Put a piece of tape between cathode tab and J/R .Because anode electrode is wider than cathode electrode.
Put the bottom tape.
Insert the finished J/R into the can manually and then short circuit check by multi-meter.
Spot welding Ni tab to cap.
Ultrasonic welding the Al tab to cap using ultrasonic weld.
We have the second spot welding to ensure the best contact between the tab and cap.
Apply top insulator, to prevent Ni tab contacting with can.
Final J/R insertion by the centrifuge.
Cap positioning by hand. Then check the cap in the suitable position, or the defects is put into red bin ,Finally , short circuit check again to ensure that there be no internal short J/R flowing to next line.
Vocabulary:
J/R 极芯tape 胶纸electrode 极片multi-meter 万用表Spot welding 点焊Ni tab 极耳Ultrasonic weld 超焊Insulator 隔圈centrifuge machine 甩壳机

本文发布于:2024-09-20 14:49:12,感谢您对本站的认可!

本文链接:https://www.17tex.com/xueshu/793783.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:胶纸   超声波   真空   手工   极片
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2024 Comsenz Inc.Powered by © 易纺专利技术学习网 豫ICP备2022007602号 豫公网安备41160202000603 站长QQ:729038198 关于我们 投诉建议