The content of this service document is the subject of intellectual property rights reserved by DNV GL AS ("DNV GL"). The user accepts that it is prohibited by anyone else but DNV GL and/or its licensees to offer and/or perform classification, certification and/or verification services, including the issuance of certificates and/or declarations of conformity, wholly or partly, on the basis of and/or pursuant to this document whether free of charge or chargeable, without DNV GL's prior written consent.DNV GL is not responsible for the consequences arising from any use of this document by others.
The electronic pdf version of this document, available free of charge CLASS PROGRAMME
Approval of manufacturers
DNVGL-CP-0346Edition May 2016DNV GL approval of manufacturer scheme
FOREWORD
DNV GL class programmes contain procedural and technical requirements including acceptance criteria for obtaining and retaining certificates for objects and organisations related to classification.
© DNV GL AS May 2016
Any comments may be sent by e-mail to rules@dnvgl
This service document has been prepared based on available knowledge, technology and/or information at the time of issuance of this document. The use of this document by others than DNV GL is at the user's sole risk. DNV GL does not accept any liability or responsibility for loss or damages resulting from any use of this document.
C
h a n g e s - c u r r e n t CHANGES - CURRENT
This is a new document.
C o n t e n t s
CONTENTS
楼恒伟案Changes - current (3)
Section 1 General (6)
2 Objective (6)
3 Scope (6)
4 Application (6)
5 Abbreviations (6)
Section 2 Approval procedure (8)
1 General (8)
2 Initial approval (9)
3 Renewal of the approval (10)
中国粉末冶金网
4 Extension or change of approved range (10) 5 Survey report (11)
6 Final approval report by manufacturer (11)
7 Evaluation by DNV GL (11)
8 Issuance of certificate (11)
9 Validity (12)
10 Suspension or withdrawal of certificates (12)
Section 3 Documentation requirements (13)
1 Introduction (13)
2 Approval report (13)
3 Statistics of previous production (13)
4 General documentation of manufacturing route and equipment (13)
5 Manufacturing summary (13)
polyview6 Manufacturer products specification (14)
杨成章7 Manufacturers’ own certificate form (14)
Section 4 Approval testing (15)
1 General requirements (15)
2 Manufacture of test products (15)
3 Witnessing of approval testing (15)
黄曲霉菌4 Testing requirements (15)
5 Retesting (16)
C o n t e n t s Appendix A : Typical procedure to be followed to obtain initial approval of manufacturer (17)
Changes – historic (18)