三级进度计划-中文

#1 NI Milestone23732007-11-30 A2014-05-31
All Elevations23732007-11-30 A2014-05-31
All Areas23732007-11-30 A2014-05-31
All Disciplines23732007-11-30 A2014-05-31
tuv
M000000000H1L001PSAR章节提交给买主里程碑02007-11-30 A
M000000000H1L161开工令里程碑02007-12-31 A
M000000000H1L006核岛负挖开始里程碑02008-02-26 A
M000000000H1L011模块预制厂可用里程碑02008-05-30 A
M000000000H1L096操作工培训的模拟器可用里程碑02008-12-01
M000000000H1L021重型吊机可用里程碑02009-08-31*
M000000000H1L016获得施工许可证里程碑02009-08-31*
M000000000H1L026第一罐混凝土开始里程碑02009-09-30*
M000000000H1L031CA20模块就位里程碑02009-11-30*
M000000000H1L036CV底封头就位里程碑02009-12-31*
M000000000H1L041CA01模块就位里程碑02010-03-31*
M000000000H1L046CV 1#环就位里程碑02010-06-30*
M000000000H1L051CV 2#环就位里程碑02010-11-30*
M000000000H1L056CV 3#环就位里程碑02011-06-30*
工程控制论 钱学森M000000000H1L061反应堆容器到达现场里程碑02011-10-31*
M000000000H1L066两台蒸汽发生器到达现场里程碑02012-02-29*
M000000000H1L071CV顶封头就位里程碑02012-04-30*
M000000000H1L081环吊可用里程碑02012-06-29*
M000000000H1L076厂用电总线通电里程碑02012-06-30*
M000000000H1L086FSAR报告提交里程碑02012-08-31*
M000000000H1L091反应堆冷却剂泵到达现场02012-10-31*
M000000000H1L101RCS系统移交里程碑02012-12-31*
M000000000H1L106屏蔽厂房穹顶完成里程碑02013-01-31*
M000000000H1L111主控室(MCR)可用里程碑02013-02-28*
M0001COMPLE需接入厂房的部分/场区移交活动02013-04-092013-04-09
M000000000H1L116冷态试验开始里程碑02013-04-30*
M000000000H1L121汽轮机蒸汽准备里程碑02013-06-28*
M000000000H1L126热态试验开始里程碑02013-06-30*
M0002COMPLE系统接入试验活动02013-08-262013-08-26
M000000000H1L131安全壳泄漏试验完成里程碑02013-09-30*
M000000000H1L136颁发装料许可证里程碑02013-10-31*
M000000000H1L141开始装料里程碑02013-11-30*
M000000000H1L146首次临界里程碑02014-01-31*
M000000000H1L151首次并网里程碑02014-02-28*
M000000000H1L156性能试验结束里程碑02014-05-31*
Yard3892010-11-152011-12-09
Auxilliary Building1962011-05-272011-12-09
Area 11962011-05-272011-12-09
Mechanical1022011-07-252011-11-04
A4803M0016H1L301场区非能动安全壳冷却补助水储存箱-机械安装702011-07-252011-11-04
Civil/Structure592011-05-272011-07-25
A4803CC016H1L301场区非能动安全壳冷却补助水储存箱- 基础402011-05-272011-07-25
Piping212011-11-042011-11-25
A4803M0016H1L306场区非能动安全壳冷却补助水储存箱 -安装管支架和管子152011-11-042011-11-25
Electrical72011-11-252011-12-02
A4803M0016H1L316场区非能动安全壳冷却补助水储存箱 -电气安装52011-11-25*2011-12-02
Actual Work Critical Remaining Work Summary Page 1 of 42Powered by Primavera Systems
Instrumentation72011-12-022011-12-09
A4803M0016H1L311场区非能动安全壳冷却补助水储存箱 -仪表安装52011-12-02*2011-12-09
Insulation352011-11-042011-12-09
A4803M0016H1L321场区非能动安全壳冷却补助水储存箱-保温和油漆252011-11-042011-12-09
Annex Building2592010-11-152011-08-01
Area 32592010-11-152011-08-01
Mechanical1672011-01-112011-06-27
A4803M0015H1L301场区除盐水储存罐-机械安装702011-01-112011-04-26
A4803M0011H1L360场区硼酸罐-机械安装702011-03-142011-06-27
Civil/Structure1192010-11-152011-03-14
A4803CC015H1L301场区除盐水储存罐-基础402010-11-152011-01-11
A4803CC011H1L301场区硼酸罐-基础402011-01-112011-03-14
六氟异丙醇Piping832011-04-262011-07-18
A4803M0015H1L306场区除盐水储存罐-管支架和管子安装152011-04-262011-05-20
A4803M0011H1L365场区硼酸罐-管支架和管子安装152011-06-272011-07-18
Electrical662011-05-202011-07-25
A4803M0015H1L316场区除盐水储存罐-电气安装52011-05-202011-05-27
A4803M0011H1L375场区硼酸罐-电气安装52011-07-182011-07-25
Instrumentation662011-05-272011-08-01
A4803M0015H1L311场区除盐水储存罐-仪表安装52011-05-272011-06-03
列藏本A4803M0011H1L370场区硼酸罐-仪表安装52011-07-252011-08-01
Insulation972011-04-262011-08-01
A4803M0015H1L321场区除盐水储存罐-保温和油漆252011-04-262011-06-03
A4803M0011H1L380场区硼酸罐-保温和油漆252011-06-272011-08-01
Diesel Generator Building2592011-01-112011-09-27
Diesel Generator Bu
All Areas2592011-01-112011-09-27
Mechanical1472011-03-282011-08-22
A4803M0012H1L301场区燃油储存罐-机械安装1002011-03-282011-08-22
Civil/Structure762011-01-112011-03-28
A4803CC012H1L301场区燃油储存罐-基础502011-01-112011-03-28
Piping222011-08-222011-09-13
A4803M0012H1L306场区燃油储存罐-管支架和管子安装152011-08-22*2011-09-13
Electrical72011-09-132011-09-20
A4803M0012H1L316场区燃油储存罐-电气安装52011-09-13*2011-09-20
Instrumentation72011-09-202011-09-27
A4803M0012H1L311场区燃油储存罐-仪表安装52011-09-20*2011-09-27
Insulation362011-08-222011-09-27
A4803M0012H1L321场区燃油储存罐-保温和油漆252011-08-222011-09-27
Turbine Building2522011-01-112011-09-20
Area 32522011-01-112011-09-20
Mechanical1542011-03-142011-08-15
A4803M0013H1L301场区冷凝水储存罐-机械安装502011-03-142011-05-27
A4803M0014H1L301场区首级和次级消防水储存罐-机械安装552011-05-272011-08-15
Civil/Structure1362011-01-112011-05-27
A4803CC013H1L301场区冷凝水储存罐-基础402011-01-112011-03-14
A4803CC014H1L301场区首级和次级消防水储存罐-基础502011-03-142011-05-27
Piping1012011-05-202011-08-29
A4803M0013H1L306场区冷凝水储存罐-管支架和管子安装. 3区152011-05-202011-06-13
A4803M0014H1L306场区首级和次级消防水储存罐-管支架和管子安装152011-08-082011-08-29
Electrical842011-06-132011-09-05
A4803M0013H1L316场区冷凝水储存罐-电气安装52011-06-13*2011-06-20
A4803M0014H1L316场区首级和次级消防水储存罐-电气安装52011-08-29*2011-09-05
Actual Work Critical Remaining Work Summary Page 2 of 42Powered by Primavera Systems
Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3 Instrumentation852011-06-202011-09-13
A4803M0013H1L311场区冷凝水储存罐-仪表安装52011-06-20*2011-06-27
A4803M0014H1L311场区首级和次级消防水储存罐-仪表安装52011-09-05*2011-09-13
Insulation1162011-05-272011-09-20
A4803M0013H1L321场区冷凝水储存罐-保温和油漆232011-05-272011-06-30*
A4803M0014H1L321场区首级和次级消防水储存罐-保温和油漆252011-08-152011-09-20
Nuclear Island (Cont
Nuclear Island (Containment Bldg & Aux. Bldg.)5832008-07-28 A2009-09-30
Base Elevation5832008-07-28 A2009-09-30
All Areas5832008-07-28 A2009-09-30
General Engineering422009-08-132009-09-23
N0003CR570H1L311核岛-第1阶段团队准备情况评估(底部标高,整个区域)22009-08-13*2009-08-14
N0003CR570H1L316核岛-第2阶段团队准备情况评估(底部标高,整个区域)12009-08-262009-08-26
N0003CR570H1L321核岛-第3阶段团队准备情况评估(底部标高,整个区域)12009-09-082009-09-08
N0003CR570H1L326核岛-最后阶段团队准备情况评估(底部标高,整个区域)42009-09-182009-09-23
Mechanical792009-06-102009-08-27
N0003CR511H1L316核岛-核岛预埋管安装、接地,底部标高,整个区域412009-06-10*2009-08-05
N0003KB111H1L301核岛-KB10,KB13模块箱体安装(WWS-MT-06, WRS-MT-01),底部标高,整个...102009-06-15*2009-06-26
N0003KB111H1L306核岛-设备地脚螺栓和预埋件安装,底部标高,整个区域102009-08-14*2009-08-27
Civil/Structure5832008-07-28 A2009-09-30
N0003EX111H1L315核岛-进行爆破技术测试,底部标高,整个区域242008-07-28 A2008-08-12 A
N0003EX111H1L320核岛-开始爆破,开挖至最终标高的3米以上,底部标高,整个区域462008-07-29 A2008-11-12 A
N0003EX121H1L301核岛-负挖及清理,底部标高,整个区域182008-07-29 A2009-02-15 A
蝙蝠侠前传2黑暗骑士在线观看
N0003EX111H1L322核岛-爆破及负挖核岛区域至最终标高,底部标高,整个区域192008-11-13 A2008-12-22 A
N0003EX122H1L301核岛-国家核安全局检查负挖,底部标高,整个区域22009-02-21 A2009-02-21 A
N0003CC470H1L301核岛-填平齐夯浇筑、接地及下垫层混凝土浇筑(包括混凝土养护和检查)...02009-03-03 A2009-04-03
N0003CC470H1L306核岛-下垫层顶部防水膜安装及检查,底部标高,整个区域72009-04-072009-04-15
N0003CC470H1L311核岛-上垫层混凝土浇筑、养护及检查,底部标高,整个区域112009-04-162009-04-30
N0003CR511H1L301核岛-底部钢筋安装及检查,底部标高,整个区域02009-05-07*2009-05-07
N0003CR511H1L306核岛-底板上层钢筋支架安装92009-05-112009-05-21
N0003CR511H1L311核岛-底板上层钢筋(包括T型钢筋、墙体插筋、4和5层钢筋)安装582009-05-202009-08-10
N0003CR560H1L301核岛-电梯井模板和免拆模板定型,底部标高,整个区域172009-08-05*2009-08-27
N0003CR560H1L306核岛-核岛底板模板安装,底部标高,整个区域132009-08-112009-08-27
N0003CC201H1L311核岛-底板混凝土浇筑,底部标高,整个区域32009-09-28*2009-09-30
Containment12162009-11-272013-03-27
Containment Buildin
Containment Building Elevation 66'6" to 71'6"422009-11-272010-01-07
All Areas422009-11-272010-01-07
Mechanical392009-11-272010-01-04
C1103MV501H1L310安全壳厂房-CR10模块底封头吊装、就位、正92009-11-27*2009-12-09
C1103ME511H1L306安全壳厂房-KQ11模块安装(标高69' 6")52009-12-28*2010-01-04
Civil/Structure152009-12-232010-01-07
C1103CC111H1L305安全壳厂房-安装整个区域的钢筋、预埋件、模板、混凝土(标高66'6'' - 71'6'')102009-12-23*2010-01-07
Containment Building Elevation 71'6'' to 84'6''4752010-01-222011-05-12
Containment Buildin
All Areas4752010-01-222011-05-12
Mechanical492010-07-132010-08-30
C1103ME511H1L301安全壳厂房-KQ10,KU05AE模块安装, 标高71' 6"352010-07-13*2010-08-30
Civil/Structure2832010-01-222010-11-01
C1133CA040H1L305安全壳厂房-模块CA04吊装、就位、正(标高71'6'')52010-01-22*2010-01-29
C1103CA050H1L305安全壳厂房-模块CA05吊装、就位、正(标高83')62010-01-22*2010-02-01火柴算式
C1103CB001H1L305安全壳厂房-CB65-66模块安装,标高71'6''52010-01-22*2010-01-29
C1103CC112H1L305安全壳厂房-安装钢筋、预埋件、模板、混凝土(标高71'6'' 至84'6'')292010-01-29*2010-03-16
Actual Work Critical Remaining Work Summary Page 3 of 42Powered by Primavera Systems
C1103CB001H1L315安全壳厂房- CB51-54,  CB61-64模块安装(蒸汽发生器区),标高80' 0"52010-02-22*2010-02-26
C1103CA010H1L315安全壳厂房-CA01模块吊装、就位、正(标高83')192010-03-31*2010-04-28
C1003AQ112H1L310安全壳厂房-楼梯模块(CS15/17)安装,标高EL 83' / EL 80' 6"202010-09-30*2010-11-01
Piping1272010-07-062010-11-09
C1103PL010H1L305安全壳厂房-整个区域的小口径管道和支架预制,标高71'6'' 至 84'6''402010-07-06*2010-08-30
C1103PL010H1L330安全壳厂房-整个区域的大口径管道和支架预制,标高71'6'' 至 84'6''402010-07-09*2010-09-02
C1103PL000H1L310安全壳厂房-整个区域的大口径支架、管子、阀门安装,标高71'6'' 至 84'6''352010-07-23*2010-09-09
C1113PL020H1L315安全壳厂房-整个区域的小口径管、支架、阀门安装,标高71'6'' 至 84'6''562010-08-18*2010-11-09
Electrical1972010-08-162011-02-28
C1133ER030H1L305安全壳厂房-电缆槽支架预制,标高71'6'' 至 84'6''(整个区域)402010-08-16*2010-10-14
C1133ER030H1L315安全壳厂房-电缆槽安装,标高71'6'' 至 84'6''(整个区域)352010-10-06*2010-11-23
C1153EF020H1L330安全壳厂房-电力设备安装,标高71'6'' 至 84'6''(整个区域)702010-10-06*2011-01-12
C1133ER030H1L320安全壳厂房-接地\照明\防火设施安装,标高71'6'' 至 84'6''(整个区域)1002010-10-062011-02-28
Instrumentation742011-02-282011-05-12
C1153JE020H1L305安全壳厂房- 支架和配管预制,标高71'6'' 至 84'6''(整个区域)252011-02-28*2011-04-04
C1153JE020H1L310安全壳厂房-仪表安装,标高71'6'' 至 84'6''(整个区域)242011-04-06*2011-05-12
Ventilation1042010-07-232010-11-03
C1103AH511H1L305安全壳厂房-HVAC风管和支架预制,标高71'6'' 至 84'6''(整个区域)302010-07-23*2010-09-02
C1103AH511H1L310安全壳厂房-HVAC设备安装,标高71'6'' 至 84'6''(整个区域)502010-08-20*2010-11-03
C1103AH511H1L315安全壳厂房-HVAC风管和支架安装,标高71'6'' 至 84'6''(整个区域)402010-08-202010-10-20
Containment Building Elevation 84'6"" to 107'2''10572010-03-022013-01-22
Containment Buildin
All Areas10572010-03-022013-01-22
Mechanical9382010-06-302013-01-22
C1203MV501H1L310安全壳厂房-CV 1#环安装焊接,标高84'6" 至107'2''192010-06-30*2010-07-26
C1233MT011H1L305安全壳厂房-标高84'6" 至107'2'',A4172010-10-18*2010-11-09
C1233MT011H1L310安全壳厂房-标高84'6" 至107'2'',A3172010-10-18*2010-11-09
C1203KQ111H1L310安全壳厂房-KQ22,KQ23模块安装,标高84'6" 至107'2''252010-10-22*2010-11-25
C1203KQ111H1L325安全壳厂房-Q223, Q233, Q240模块安装,标高84'6" 至107'2''152010-10-22*2010-11-11
C1203KQ111H1L330安全壳厂房-KU-05AW, KU-05AC, KU05-AR, KU05-AL模块安装, 标高 82'6"52010-11-102010-11-16
C1203KQ111H1L320安全壳厂房-KU-05AJ模块安装,标高96' 6", A 452010-11-172010-11-23
C1203KQ111H1L312安全壳厂房-KU20CVA,KU020CVB模块安装(高压过滤器/楼板模块),标高84'6" 至107'2''52010-11-19*2010-11-25
C1203KQ111H1L305安全壳厂房-KU-05AX, KU-05AD, KU-05AM, KU-05AS模块安装, 标高100' 0" 至 107'2''52010-11-242010-11-30
C1233ME111H1L310安全壳厂房-下部内件存放台安装,标高84'6" 至107'2''132011-03-252011-04-13
C1223FS001H1L305安全壳厂房-燃料储存架安装,标高84'6" 至107'2''. 4区272011-03-25*2011-05-06
C1233ME111H1L315安全壳厂房-上部内件存放台安装,标高84'6" 至107'2''142011-04-142011-05-06
C1203KQ111H1L335安全壳厂房-Q305, Q303模块安装,标高84'6" 至107'2''52011-08-22*2011-08-26
C1223MV010H1L305安全壳厂房-反应堆容器支架安装和调整182011-10-252011-11-18
C1223MV010H1L310安全壳厂房-反应堆容器安装,标高84'6" 至107'2''122011-11-18*2011-12-06
C1203MB010H1L305安全壳厂房-蒸汽发生器1A安装、正,  标高84'6" 至107'2''152012-01-30*2012-02-20
C1203MB011H1L305安全壳厂房-蒸汽发生器1B安装、正,  标高84'6" 至107'2''152012-02-29*2012-03-21
C1223MI001H1L310安全壳厂房-反应堆容器内下部内件的进入和嵌入502012-07-04*2012-09-11
C1223MI001H1L315安全壳厂房-反应堆容器内上部内件的进入和嵌入502012-09-122012-11-26
C1203MP011H1L305安全壳厂房-RCS-MP-01A反应堆冷却泵安装,标高84'6" 至107'2''282012-10-22*2012-11-28
C1223FH070H1L305安全壳厂房-燃料传输管/设备安装,标高84'6" 至107'2''302012-10-22*2012-12-03
C1203MP011H1L310安全壳厂房-RCS-MP-02A反应堆冷却泵安装,标高84'6" 至107'2''282012-10-24*2012-11-30
C1203MP011H1L320安全壳厂房-RCS-MP-01B反应堆冷却泵安装,标高84'6" 至107'2''262012-10-26*2012-11-30
C1203MP011H1L325安全壳厂房-RCS-MP-02B反应堆冷却泵安装,标高84'6" 至107'2''262012-10-30*2012-12-04
C1203MV101H1L305安全壳厂房-反应堆容器集成一体化顶盖安装,标高84'6" 至107'2''402012-11-27*2013-01-22
C1203MV101H1L310安全壳厂房-反应堆容器螺柱紧固102013-01-09*2013-01-22
Civil/Structure3702010-03-022011-03-07
Actual Work Critical Remaining Work Summary Page 4 of 42Powered by Primavera Systems
C1203CC111H1L305安全壳厂房-钢筋、预埋件、模板安装,混凝土浇筑,标高84'6" 至107'2''1302010-04-28*2010-11-08
C1203CB002H1L325安全壳厂房-CB21模块安装,标高83'52010-05-31*2010-06-04
C1203CB002H1L310安全壳厂房-CB24-25, CB31-33, CB41-43模块安装,标高87' 6"202010-06-07*2010-07-05
C1203CB002H1L315安全壳厂房-CB37-39模块安装, 标高94'102010-07-19*2010-07-30
C1203CB002H1L320安全壳厂房-CB26-28, CB34-36, CB44-47模块安装, 标高 96'202010-08-16*2010-09-10
C1203CA031H1L305安全壳厂房- CA03 模块安装, 标高 96'112010-09-24*2010-10-13
C1203CA021H1L305安全壳厂房- CA02 模块安装, 标高 103', A 282010-10-15*2010-10-26
C1203CA003H1L305安全壳厂房-CA34-37模块安装, 标高 107'2''122010-12-03*2010-12-20
C1203CA003H1L315安全壳厂房-CA32-33模块安装, 标高107'2''72010-12-21*2010-12-29
C1203CC002H1L305安全壳厂房-安全壳内换料储水箱衬里,标高84'6" 至107'2''352011-01-12*2011-03-07
Piping5272010-12-222012-05-31
C1203PL040H1L305安全壳厂房-大口径管道及支架预制,标高84'6" 至107'2''652010-12-22*2011-03-29
C1203PL040H1L320安全壳厂房-小口径管道及支架预制,标高84'6" 至107'2''502011-01-04*2011-03-18
C1203PL030H1L305安全壳厂房-大口径管支架、管道及阀门安装,标高84'6" 至107'2''902011-03-03*2011-07-14
C1213PL030H1L305安全壳厂房-小口径管支架、管道及阀门安装,标高84'6" 至107'2''1302011-05-26*2011-11-30
C1223PL211H1L305安全壳厂房-反应堆冷却系统主回路管道引入,标高84'6" 至107'2''52011-10-20*2011-10-27
C1223PL211H1L310安全壳厂房-反应堆冷却系统主回路管支架安装,标高84'6" 至107'2''202012-01-18*2012-02-20
C1223PL111H1L305安全壳厂房-反应堆冷却系统主回路管道冷支腿安装,标高84'6" 至107'2''682012-02-202012-05-31
C1223PL111H1L310安全壳厂房-反应堆冷却系统主回路管道热支腿安装,标高84'6" 至107'2''682012-02-202012-05-31
Electrical2702011-04-012011-12-26
C1233ER040H1L305安全壳厂房-电缆线槽和支架预制,标高84'6" 至107'2''(整个区域)702011-04-01*2011-07-14
C1233ER040H1L315安全壳厂房-电缆线槽和支架安装,标高84'6" 至107'2''(整个区域)602011-05-192011-08-11
C1233ER040H1L320安全壳厂房-接地\照明\防火设施安装,标高84'6" 至107'2''(整个区域)622011-05-192011-08-15
C1253EF040H1L305安全壳厂房-电气设备安装,标高84'6" 至107'2''(整个区域)1082011-07-22*2011-12-26
Instrumentation1502011-12-262012-05-24
C1253JE040H1L310安全壳厂房-仪表管支架预制安装,标高84'6" 至107'2''902011-12-26*2012-05-10
C1253JE040H1L305安全壳厂房-仪表安装,标高84'6" 至107'2''802012-01-27*2012-05-24
Ventilation2662011-03-032011-11-23
C1233AH111H1L305安全壳厂房-HVAC风管及支架预制,标高84'6" 至107'2''1002011-03-03*2011-07-28
C1233AH111H1L315安全壳厂房-风管和支架安装,标高84'6" 至107'2''1502011-04-18*2011-11-23
C1233AH111H1L310安全壳厂房-HVAC设备安装,标高84'6" 至107'2''1182011-05-202011-11-08
Insulation3022011-08-312012-06-28
C1223MN111H1L305安全壳厂房-金属反射保温安装-在安装反应堆容器之前的反应堆腔壁上,标高84'6" 至10...202011-08-31*2011-09-29
C1223MN112H1L305安全壳厂房-RCS,RXS主设备/管道保温,标高84'6" 至107'2''(整个区域)352012-05-09*2012-06-28
Containment Building Elevation 107'2"" to 118'6''6112010-12-302012-08-31
Containment Buildin
All Areas6112010-12-302012-08-31
Mechanical2722011-03-232011-12-19
C1303MT021H1L305安全壳厂房-堆芯补给罐PXS-MT-02A/B安装,标高 107'2"202011-03-23*2011-0
4-20
C1303ME111H1L305安全壳厂房-机械设备安装,标高107'2" 至118'6"1302011-03-23*2011-09-28
C1303MW010H1L305安全壳厂房-反应堆冷却降压喷洒器PXS-MV-01A/B安装152011-04-21*2011-05-16
C1303ME030H1L305安全壳厂房-非能动余热去除热交换器安装122011-11-29*2011-12-15
C1303MV201H1L305安全壳厂房-稳压器(RCS-MV-02)安装72011-11-30*2011-12-09
C1303MV201H1L310安全壳厂房-稳压器侧向支撑安装62011-12-092011-12-19
Civil/Structure5342010-12-302012-06-15
C1333SS111H1L305安全壳厂房-钢结构、CH59模块及格栅板安装,标高107'2" 至118'6"542010-12-30*2011-03-22
C1313CC111H1L310安全壳厂房-钢筋、预埋件、模板安装及混凝土浇筑,标高107'2" 至118'6"182011-03-23*2011-04-18
C1003AQ112H1L315安全壳厂房-CS11楼梯模块安装,标高107'2" 至118'6"202011-04-19*2011-05-19
C1333CA311H1L310安全壳厂房-CA31模块安装, 标高107'2"102012-06-04*2012-06-15
Piping4162011-04-122012-05-31
C1303PL040H1L310安全壳厂房-大口径支架和管道预制,标高107'2" 至118'6"(整个区域)692011-04-12*2011-07-22
Actual Work Critical Remaining Work Summary Page 5 of 42Powered by Primavera Systems

本文发布于:2024-09-22 22:20:44,感谢您对本站的认可!

本文链接:https://www.17tex.com/xueshu/249598.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:安装   标高   里程碑   厂房   模块
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2024 Comsenz Inc.Powered by © 易纺专利技术学习网 豫ICP备2022007602号 豫公网安备41160202000603 站长QQ:729038198 关于我们 投诉建议