英文原版施工方法-BS标准

1Structure Works
1.1Site Survey
General information
This project is made of 1269 sets villas。 Most villas are 2 layers and parts are 3 layers.
Entering site
泰诺星球
Before constructing, with the help of the survey engineer sent by the client, the map of plane control point, coordinate, location of point, elevation and the survey position systems that are offered by the client should be received.
To get correctly conditions of the control point and survey position system, the plane control network should be checked, which is offered by the client。 When checking, GPS and Electronic Tacheometer can be used, and rigorous adjustment must be adopted. The checked result should be report to the client and supervisor engineer。
Erection of the site control network
Erection of the horizontal control network
According to horizontal control point offered by the client, a whole horizontal control network in site should be erect。 The erection of the horizontal control network should be divided into the first class and the second class。 Adopt GPS to erect the first class control point every 300m and adopt Electronic Tacheometer to erect the second class point every 100m. The adjustment should be rigorous.
Erection of the elevation control network
According to elevation control point offered by the client, 3 leveling points should be erect at right place in site. Annexed leveling should be adopted to achieve the elevation of the three control points and the others in other field。 So the elevation of control points is coherent。 Transfer the height system of the control points to working field to control construction。 The second horizontal control point can be accordance with the elevation control point. The error should be fit to the locate criterion.
Construction survey
人工呼吸机Erection of the building horizontal control network
According with the second step horizontal control network, erect construction axis control network of every building, and pairs of control points must be the only form. The control points should be 500m or 1000m away from axis。
Erection of the building elevation control network
According with the elevation control points, adopt annexed leveling to erect building elevation points to control vertical construction.
Foundation construction survey
Due to isolate foundation pit is not very deep, so lead the axial control network that had been erected to foundation pit and check the relation between the axis。 If the relation is correct, fine part line, excavation line, column location line and control line can be lay
out. Through elevation control point on ground with leveling instrument, elevation of foundation pit and foundation construction can be controlled.
Construction survey of structure on the ground
when the construction height achieve to height ±0.000, the axis should be lay out。 Check it and lay out the axis to the column and above floor。
Line out the height
On every building, measure level line 1.00m from the first floor vertical structure, mark three points on this line, draw ruler from these three points to form relative three points when construction is on the top of the structure, collate the elevation point that had been transferred from the first floor before leveling 。If the relation of the points transferred is correct, lead horizontal line 1。00m to outside of the structure according with elevation of the average point to control construction of plane structure of every floor.
Finishing and equipment installation survey
Lead axis of structure construction to outside construction and make marks, which will control outside installation。 Every room of construction should be made “+” line on ground, each wall and ceiling, which will control inside installation.
氢溴酸Surveyors
Because this project is huge, the survey workload is big and the time limit for a project is short, professional survey engineers and comparative surveyors will be needed。
1.2Formwork
Selection of formwork system
According to the character of this project construction, steel form is used in columns and wood form is used in beams and boards.
The form materials and requirements must conform to the specification。
Formwork construction
Foundation formwork
我所认识的蔡孑民先生>电路板识别
The installation procedures are as follows:
Leveling Setting out彭罗斯brush the release agent Erecting the formwork from the middle sectionErecting the horizontal rib and diagonal brace  Setting up the shoring shelfChecking and re-adjusting
The formwork of foundation chooses small steel form to assemble。 The sketch of formwork see below:

本文发布于:2024-09-21 13:54:55,感谢您对本站的认可!

本文链接:https://www.17tex.com/xueshu/121674.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:孑民   先生   识别
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2024 Comsenz Inc.Powered by © 易纺专利技术学习网 豫ICP备2022007602号 豫公网安备41160202000603 站长QQ:729038198 关于我们 投诉建议